As per the projections in the 10th and 11th Five Year Plan
of the Govt. of India, new capacity addition in Power Generation
have been projected as 1,10,000 MW. This translates to an
investment of Rs. 4,000 billion (USD 90 billion) approximately in
the power generation field. Correspondingly there will be huge
investment in the transmission and distribution area which is
estimated to be about Rs. 4500 billion (USD 101 billion).
Considering the vast potential for growth and investment in this field,
GEI has embarked into the power sector field.
A separate business group viz. GEI- Power Transmission Business
Group has been created in the company. A first order of more than
Rs. 100 million (USD 2.25 million) has been received which covers
Rural Electrification of 400 villages, erection of four new Switchyards
of 33/11 KV, 5 MW each and augmentation of seven existing switchyards
and is being executed. Very shortly, the company proposes to enter into
the Power Transmission area upto 132 KV. While major electrical equipment
will be outsourced, structures will be manufactured in-house. Other activities
like erection, commissioning and testing will be carried out by the company.
Experts in these fields have been recruited in the company recently.
The company also proposes to enter into the field of Captive Power
Plants very shortly. While turbine and generators will be outsourced,
the other equipment like LP/HT Heaters, Deaerator, air cooling systems,
fabrication of structures etc. are proposed to be manufactured in house.
The company also proposes to enter into the field of Generator components,
heavy fabrication and machining of generator components.
It is proposed to expand this business sector to the tune of Rs. 2.5 billion
approx. (USD 56 million) in the next 4-5 years.
|
| Capabilities : |
|
At present we are engaged in the field of 33 KV sub-stations,
including control buildings, erection of new sub-stations,
upgradation/renovation of existing sub-stations, capacity
augmentation of switchyards. We have enough capability and
experienced and qualified manpower for executing Switchyard
Project in Higher KV range also. Our experienced manpower
includes engineers who have experience with BHEL, Power
Grid Corp. of India (PGCIL) and ABB.
We have sufficient capability - technical and financial - to
take up turn key projects for Switchyards, 11 KV distribution
sub-station in Rural Areas under the RGGVY scheme.
|
| Existing Projects: |
|
At Bijnor, Uttar Pradesh under RGGVY scheme of Govt. of India -
This project consist of complete survey - inside and outside
village, 33 KV main line, 11 KV spur lines and 11 KV feeder lines
of more than 500 KMs. This turn-key project of value more than
Rs. 320 million (USD 7 million) is being executed through UB
Engg./EPI for Paschimanchal Vidyut Vitaran Nigam Limited (PVVNL).
Meerut, UP. The Project includes Engineering Supply, Erection,
Testing, Commissioning of 11 KV HVDS in more than 350 villages
and also laying of 33 KV lines (more than 50 KM), 11 KV
Lines (more than 300 KM), 5 New Switchyards and augmentation
of 7 existing Switchyards.
|
|
|
 |
 |
|